RACINE COUNTY                      
FIVE YEAR CAPITAL IMPROVEMENTS PLAN   PARK DEVELOPMENT        
    PRIOR YEARS APPROVED     CAPITAL 5 YEAR PROPOSED PROJECT        
  1st Line               TOTAL REVENUE
 Description Year Total 2000 2001 2002 2003 2004 2005 2006 2002-2006 2002-2006
                     
Bike Trail Fox River Bridge to CTH "D" 2000 473,000 473,000             0 0
Bike Trail Racine to Sturtevant (CMAQ) 2000 360,000 60,000     300,000       300,000 (240,000)
Bike Trail Burlington to Waterford 2001 341,000   341,000           0 0
Bushnell - Restroom  ADA Improvements/Renovations 2000 31,000 6,000           25,000 25,000 (25,000)
Bushnell - Restroom (West side of STH 142) 2002 60,000     60,000         60,000 (60,000)
Bushnell - Trail Extension 2002 10,000     10,000         10,000 0
Bushnell - Ball Diamond Lighting and Fence 2003 20,000       20,000       20,000 (20,000)
Bushnell - Ball Diamond Lighting 2004 50,000         50,000     50,000 (25,000)
Case Eagle - Restroom/Concessions  2000 90,000 10,000   80,000         80,000 0
Case Eagle - Well and Sanitary Sewer 2002 45,000     45,000         45,000 0
Case Eagle - Landscaping 2002 30,000     15,000   15,000     30,000 0
Case Eagle - Arch/Construction - Shelter/Restroom 2003 109,000       9,000   100,000   109,000 0
Case Eagle - Arch/Construction - Service Building 2004 107,000         7,000   100,000 107,000 0
Case Eagle - Ball Diamond Lighting 2004 80,000         80,000     80,000 0
Case Eagle - Playgrounds/Play Equipment 2004 60,000         40,000   20,000 60,000 0
Case Eagle - Athletic Fields Development 2005 40,000           40,000   40,000 0
Case Eagle - Canoe Launch Site 2006 20,000             20,000 20,000 0
Case Eagle - Parking Lot and Road Improvements 2000 160,000 40,000 60,000   60,000       60,000 0
Cliffside Park - Restroom/Shelter Area #1 2002 80,000     80,000         80,000 0
Cliffside Park - Water/Sanitary Sewer 2002 20,000     20,000         20,000 0
Cliffside - Restroom  ADA Improvements/Renovations 2003 67,000       7,000 60,000     67,000 0
Cliffside Park - Shelter/Concession #3 2004 6,000         6,000     6,000 0
Cliffside Park - Ball Diamond Lighting 2005 40,000           40,000   40,000 0
Cliffside Park - Campground Waterline Renovation 2006 60,000             60,000 60,000 0
Cliffside Park - Campground Subsurface Drainage 2006 20,000             20,000 20,000 0
Fischer Park - Play Equipment 2005 30,000           30,000   30,000 0
Pritchard - Ice Rink 2001 4,025,000   25,000 4,000,000         4,000,000 0
Pritchard - Park Road & Parking Lot 2001 50,000   50,000           0 0
Pritchard - Maintenance and Restrooms Building 2002 80,000     40,000 40,000       80,000 0
Pritchard - Ball Diamond Lighting 2003 80,000       80,000       80,000 0
Root River Parkway - Canoe Launch 2004 40,000         40,000     40,000 0
Root River Parkway - Trail Construction 2005 50,000           50,000   50,000 0
Sanders - Parking Lot Expansion 2005 30,000           30,000   30,000 0
Sanders - Shelter 2006 40,000             40,000 40,000 0
Sanders - Campground Upgrade 2003 50,000       50,000       50,000 0
WR Wadewitz Nature Camp - Barn Remodeling 2006 50,000             50,000 50,000 0
  0                  
                     
ITEMS UNDER $20,000 COMBINED     15,000 18,000 0 0 0 0 0 0 0
                     
TOTALS     604,000 494,000 4,350,000 566,000 298,000 290,000 335,000 5,839,000 (370,000)
                     
LESS:  REVENUES     (447,000) (272,800) (60,000) (260,000) (25,000) 0 (25,000) (370,000)  
                     
NET COUNTY EXPENDITURES     157,000 221,200 4,290,000 306,000 273,000 290,000 310,000 5,469,000  