C94 (19c-1)

Back Up

RACINE COUNTY CAPITAL PROJECT REQUEST Package Number:  C94
Capital Type: (Below) Project Title: ROAD CONSTRUCTION CTH G
  Technology   Project Location: MAIN STREET TO STH 32
X Construction   Project Contact Person: CECIL MEHRING
  Equipment/Furniture   Department: PUBLIC WORKS - HIGHWAY Project ID:  2002-03
      Has this package been adjusted from prior year submission: (yes or no)  
      If this has been modified please identify where and why.
Scope and Description of Project (What)        
Text Box: The section from STH 32 to just east of Chester Lane would be reconstructed to an urban cross-section with curb, gutters and storm sewers.  The intersection with Chester Lane would be improved to provide left-turn lanes.  East of Chester Lane, the road would be transitioned back to a two-lane rural cross-section.  From this point east to North Main Street work would consist of base patching and milling the existing pavement to restore crown and improve the ride.  The milled surface would be paved with 3" to 4" of bituminous pavement.  Some minor ditching would be done to improve drainage and existing shoulders would be restored.
               
               
               
               
               
               
Justification of Project (Why)          
Text Box: The road was last resurfaced in 1987.  This section of the road has numerous patches due to storm-sewer installations and other utility work.  Four Mile Road carries in excess of 9000 vehicles per day.  The ride is very rough.  The 1996 pavement rating was 4.5 and 5.
               
               
               
               
               
Alternatives              
Text Box: Do nothing.
               
               
               
               
Impact of not accepting project          
Text Box: Continue to patch areas as they fail.  Place thin overlay to address rideability only.
               
               
               
               
Budget Summary 2002 2003 2004 2005 2006 Total
Expenses/Detail     520,000       520,000
                0
                0
                0
                0
Revenues/Sources   (260,000)       (260,000)
                0
                0
Net County Cost: 0 260,000 0 0 0 260,000
If the project contains more detail than can be supplied above please only put the summary information above
and attach a sheet showing the detail items.
               
Cost of Operating Expenses 2002 2003 2004 2005 2006 Total
Associated with Project:            
Operational Package Number for current year budget only: