This Five-year Capital Plan for Racine County details the County’s capital
requirements for the next five years, 2003-2007. The County Executive has
reviewed five-year objectives with department heads and decided which projects
to include in the Plan. The Five-year Capital Plan is now presented to the
Racine County Board.
The funding for these projects will come either from transfers from reserves or
from borrowing. In the past, the County has funded capital items primarily from
reserves and surpluses. However, borrowing will be necessary in order to
implement the attached plan, primarily due to the inclusion of a major jail
project, which could begin in the year 2003.
This document is intended to inform the County Board and taxpayers of future
requirements for capital expenditures and identifies capital costs and revenues
associated with the projects included. While precise costs are stated whenever
possible, in some cases only estimates are provided because for those items it
is neither feasible nor practical to determine exact costs. In addition, it is
important to keep in mind that, as with all long-range plans, situations can and
will change, requiring that the plan be modified as time passes.
The summary page shows that the total five-year (2003 – 2007) expenditures for
the plan and possible funding sources. The total of the 2003 Five Year Capital
Plan is $46,597,108. A history of the past two years of county capital
expenditures is also included on the summary page. Detail sheets providing
additional information about major projects are provided after the summary
schedules. The definition of a major project is a construction project that
costs more than $500,000 or an equipment purchase in excess of $250,000.
Sheriff's Department Projects
As stated previously, the major project shown in this plan is a $14 million jail
addition. A special County Board committee is currently studying this item and
will issue recommendations. Outdated communications technology requires the
County to replace systems in the future.
Road and Bridge Projects
The County is responsible for 335 lane-miles of County trunk highways, 16 County
bridges and numerous smaller drainage structures. The Highway division, in order
to capture transportation aids, has always maintained and yearly updated a
Five-year capital plan. The division has a number of projects ready to begin
construction as funding becomes available. This strategy strives to maximize
state and federal aids by having an inventory of project plans ready when funds
are being allocated by the DOT. This source of revenue for future periods must
be estimated and is subject to state and federal controls. These DOT funds are
project-specific and may or may not be the projects of the highest priority as
determined by our Highway staff. County funds not used as match funding for
state and federal projects are available to fund projects not eligible for state
or federal funding. In the past, much of the funding has come from the use of
Highway reserves. The amount of surpluses available each year varies.